Specification:
- Services pairs 600,000 / unit
- Installation refrigerant pipe (3/8 “x 5/8”) Rp.125.000 / meter
- Installation Cable control (4 x 2.5 mm) 30,000 / meter
- outdoor Bracket 200.000 / set
- Installation Cable power (4 x 4 mm) Rp.55.000 / meter
- Installation of drainage pipes (PVC ¾ “) Rp.35.000 / meter
- Accessories unit (Longrat) 150,000 / unit
- Installation Accessories (Besi UNP uk. 50 x 50 & Longrat) 25.000 / pcs
- Tools (Not including Crane) 200.000 / unit
- scafolding 1 s / d 3 interchanges (if a height above 3 meters) of 150,000 / sets
- Test commissioning (including Vacuum & addition Freon) Rp 700,000 / unit
- MCB 3 Phase Rp.350.000 / unit
- Planting sleep Cost Installation Refrigerant Piping / PVC without walls perapihan 50.000 / meter (if required)
- Iron Tracks for Outdoor placement Rp.400.000 / unit (If the outdoor placement position does not allow use Bracket outdoor)
- outdoor Safety Framework Rp 700,000 / unit (if required)